| | | | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Rural Water ProgrammeAn allocation of €1,898,000 was received from the Department of the Environment, Heritage and Local Government in respect of 2007 made up as follows:
The allocation under the Small Schemes Programme is being used to fund:
Work is in progress on these projects. Tenders were sought during the year for the Glack Group Scheme and work commenced at the end of October. The estimated cost of the scheme is €1.53m and when constructed it will supply water to approximately 92 houses and for use in agriculture. The Doo Group Scheme for which tenders were also sought during the year is due to commence in December 2007. This scheme will serve approximately 47 houses and 16 farms and is estimated to cost approximately €355,000. Substantial upgrading work was carried out on the Keash Group Scheme during the past few years. However as the scheme has been in place for over 30 years and there are still problems with leakage tenders were sought for the provision of further pipelines in the current year. The estimated cost of the proposed work is approximately €877,000. An application has been submitted for CLAR funding to fund part of the work which is expected to commence in December, 2007. Planning is in progress for the provision of new group schemes at Mullaun (Cloonacool), Ballintogher/Gortlownan/Crossboy and Coolaney Road, Collooney and it is expected that work will commence on these schemes in 2008. Work has been completed on the upgrading of the Monasteraden group scheme and this scheme is expected to be taken in charge in December, 2007. Work is also nearing completion on the Carnduff, Barnadrahy, Drinaghan, Carns (Aclare) and the Carrowlobaun Group Schemes and these schemes are also expected to be taken over in December, 2007/January, 2008. WATER SERVICES INVESTMENT PROGRAMMEThe Water Services Project Office has responsibility for Project Management and Administration of all Water Services infrastructural development projects funded via the Capital Programme, Service Land Initiatives, the Rural Water Programme and also Development Levy Schemes (funded entirely by Sligo County Council). It is the policy of Sligo County Council to bundle suitable schemes in order to deliver best value for money based on the principle of economies of scale. During 2007 a total of 52 schemes were advanced under these programmes with an overall budget estimate of €197M. Sligo Main Drainage (DBO Project)This project involves the Design Build & Operation of a new Wastewater Treatment Plant (50,000pe), Pumping Station and Sludge Hub Centre at Finisklin, Sligo to service the existing and future needs of Sligo City and its environs. The design/build phase of the scheme commenced in October 2006 and works are currently well advanced on site. The plant is due to be commissioned in October 2008. The estimated project cost is €29M. Advance works for this project were carried out in 2002 on the site and approach roads at a cost of €8M. Enniscrone Wastewater Treatment Plant (DBO Project)This scheme involves the Design Build & Operation of a new Wastewater Treatment Plant and Sludge Satellite Station in Enniscrone (5000pe) and the operation of six additional WWTP’s (Ballysadare 4500pe, Aclare 750pe, Cloonacool 500pe, Dromore West 2500pe, Coolaney 2500pe and Easkey 450pe). The contract was signed with EPS Ltd. on 23rd March 2007. Construction of Enniscrone WWTP is currently well advanced and will to be commissioned in 2008. The estimated project cost is €4.9M. Teesan / Lisnalurg Sewerage SchemeThis scheme involves the construction of 2.7km of foul sewers, 1.1km of storm sewers, 3.8km of watermains, one foul sewage pumping station and 0.8km twin rising main pipelines to service the entire zoned catchment area in Teesan Lisnalurg. The planning and procurement for the scheme was completed during 2007 and construction is due to commence in April 2008. The estimated cost of the scheme is €3.7M. Kilsellagh Water Treatment Plant (DBO Project)This scheme involves the Design Build & Operation of a new Water Treatment Plant at Kilsellagh, approx. 6.5km North East of Sligo town. The plant will have a maximum throughput capacity of 400m³/hr. The operation contract will include the existing impounding reservoir. The Report on Tenders has been submitted to the DEHLG. It is anticipated that the contract will commence during the second quarter of 2008. The contract period is 15 months. The estimated project cost is €9.62M. Tubbercurry Grange and Strandhill Wastewater Treatment Plants (DBO Project)These three schemes involving the provision of new wastewater treatment infrastructure for the towns of Tubbercurry (5000 Population Equivalent), Grange (2500PE) and Strandhill (4500PE) are to be advanced as a single DBO project. The upgrade of Ballinafad WwTP has also been added to this project to deliver further value for money. The closing date for the tender period is 14th March 2008. It is anticipated that the contract will be awarded during 2008. The average cost estimate in the Design Review Report is €9.24M. It is also noted that advance works were carried out at the Tubbercurry WwTP during 2007 in accordance with an EPA Direction. Carraroe Sewerage Scheme – Stage AThis element of the Carraroe Sewerage Scheme is being funded entirely by Sligo County Council from Development Levies. This scheme involves the installation of a foul sewage collection system complete with pumping stations and rising mains as required toservice lands zoned as WILT in the Carraroe/Ballydredhid area. The purchase of existing infrastructure built by private developers will be an integral part of the project. Planning and procurement of the scheme is ongoing and it is anticipated that construction work will commence in 2008. The preliminary cost estimate for the scheme is €4M. Carraroe Sewerage Scheme - Stage BA Preliminary Report was prepared in 2002 for the provision of foul and storm water drainage on a 395 hectare study area from Carraroe to Ballydrehid. The DEHLG recommended revision of the PR to incorporate SUDS techniques in stormwater collection and disposal. Work on the revised PR has commenced and will be completed during 2008. Cost estimate for this element of the project is €2.6M. Sligo Sewerage Scheme (Network Improvement)This project relates to proposed improvement works to the existing combined sewer network in Sligo City. The preliminary report highlighted 28 sections of the network which require improvement works based on network modeling and local knowledge. It is proposed to commence works at three locations in 2008, Pearse Road, O’Connell Street and along the railway track at Thornhill. It is also proposed to carry out CCTV surveys on other parts of the network to establish a prioritized schedule of works which will be advanced to construction stage on a phased basis. The total project cost is estimated at €5.7M. Lough Talt Regional Water Supply Scheme (DBO Project)The initial phase of this scheme involves the preparation of a Preliminary Report to assess demands, sources and treatment options for the Lough Talt WSS. Work has been ongoing throughout 2007 on data collection, raw water sampling, demand modelling, asset review, source assessment and network model analysis. The Preliminary Report cost estimate for the entire scheme is €34.65M. Consultations are ongoing with the relevant prescribed bodies in relation to the EIS and water abstraction requirements for the scheme and this process will be advanced during 2008. Water Conservation and Network Management ProjectThe County Sligo Water Conservation and Network Management Project is sub-divided into three stages;
Stage 1 is practically complete and Stage 2 has already achieved a reduction in water production of 5546m³/day in the Sligo County & Borough areas. A detailed report on Stage 3 mains rehabilitation for the county area has being prepared and submitted to the DEHLG for approval. A similar report for the borough area will be submitted during 2008. Advance funding of €2M for Stage 3 is currently being sought from the ERDF. A Strategic Operational and Management Plan is currently being prepared which will address the following:
The fundamental objective of the strategic plan will be the continued provision of a safe, adequate and secure water supply for the people of Sligo. Cost Estimates for Stage 1 and Stage 2 is €3.42M, and for Stage 3 in the county area is €39.4M. Rosses Point / Cregg / Ballincar Sewerage SchemeThis scheme relates to the provision of three pumping stations and associated pipeline infrastructure for the transfer of raw sewage effluent from the Ballincar, Cregg and Rosses Point catchments to Sligo Main Drainage WWTP for treatment. Site investigation works have been completed and draft Contract Documents are being prepared. Two pump station sites have been identified and Part 8 planning will be progressed. The estimated cost of the scheme in the PR is €3.9M. Sligo Main Drainage Stage VI – Cumeen Sewerage SchemeThis scheme involves the installation of a sewerage collection system to service existing development in the Cumeen area. The cost estimate for the provision of new infrastructure is €2.3M. The purchase of existing infrastructure built by private developers will be an integral part of the project. Work is ongoing on the completion of the Design Review Report and pending formal DEHLG approval the scheme will be advanced to the procurement phase in the current year. Ballygawley, Mullaghmore, Cliffoney and Ballinacarrow Sewerage SchemesThese four village schemes involving the provision of new wastewater infrastructure were progressed as a single project for the preparation of preliminary reports. Ballygawley and Mullaghmore have been approved under the Capital programme while Cliffoney and Ballinacarrow are approved as Service Land Initiative Schemes. The preliminary reports cost estimates for completion of the entire schemes are; Ballinacarrow €3.3M; Cliffoney €5M; Ballygawley €3.6M; Mullaghmore €9.5M. DEVELOPMENT LEVY SCHEMESDevelopment Levy Schemes are funded from development levies charged in accordance with Section 48 of the Planning and Development Act 2000. This mechanism allows Sligo County Council to provide new infrastructure thereby facilitating development that would not be feasible otherwise. New wastewater treatment plants funded entirely from Development Levies have been completed in Coolaney, Dromore West and Carney during 2007. Gurteen Wastewater Treatment WorksThe new 2,500pe wastewater treatment plant in Gurteen is currently being commissioned and it is anticipated that the plant will be completed in April, 2008. The estimated cost for this scheme is €1,622,993. Coolaney Water SupplyThis scheme involves the installation of approximately 1km of 150mm diameter rising main and the construction of a new reservoir to provide 522m³ water storage capacity in the Coolaney area. The rising main is complete and works on the reservoir are substantially complete. It is anticipated that this new water supply infrastructure will be fully operational in April 2008. The cost estimate for the scheme is €252,000. Ballintogher Wastewater Treatment WorksThis project involves the construction by a private developer of a new 1500PE wastewater treatment works in the village of Ballintogher. A Special Contributions Scheme of €9,000 / unit has been put in place in Ballingtogher. It is anticipated that Part 8 Planning and procurement for the scheme will proceed in 2008 subject to formal agreement between Sligo County Council and the developer. The cost estimate for the scheme is €1,420,345. Castlebaldwin Wastewater Treatment WorksThis project involves the construction by a private developer of a new 1000PE wastewater treatment works in the village of Castlebaldwin. A Special Contributions Scheme of €9,000 has been put in place in Castlebaldwin. It is anticipated that Part 8 Planning and procurement for the scheme will proceed in 2008 subject to formal agreement between Sligo County Council and the developer. The cost estimate for the scheme is €1,393,680. Rockfield Wastewater Treatment WorksThis project involves the upgrade by a private developer of the wastewater treatment plant in the village of Rockfield. The upgraded plant will have a design capacity of 250PE. Sligo County Council has undertaken the completion of this scheme as a consequence of default by the developer to complete the works. The estimated cost of the scheme is €175,000. Raghly Harbour Improvement SchemeDuring 2005 a new slipway was constructed in Raghly Harbour as the first phase of a major improvement scheme. The project was conceived with the community group and promoted in partnership with the Community and Enterprise Directorate during 2003 and 2004 who secured Phase II funding for the slipway and other ancillary works. The Infrastructure Directorate took on the management of the contract to build the slipway which was completed in September 2006. The Department of Communications, Energy and Natural Resources funding for the much larger Phase II project involving a new quay, new jetties, dredging and ancillary works was secured by the Infrastructural Directorate, with an allocation of €0.845m in 2006. Love Contracts was awarded the contract which has a number of difficult aspects that are being overcome. Delays in commencement of Phase II has resulted in a shortfall in funding which has not kept pace with increased costs in construction, however, the bulk of the essential works were completed by Christmas 2007. The new protected harbour area was opened last autumn. Additional funding has been sought from the Department of Communications, Energy and Natural Resources to fully complete the project. The Project Engineer for the scheme is Gary Salter and Dessie Sloyan is the Resident Engineer, Consultants - SDS Ltd, Contractor - Gerald Love Contracts. Bunannaden Wastewater Treatment WorksThis scheme involves the construction by a private developer of a new 350PE wastewater treatment works in the village of Bunannaden. The new plant will have potential for upgrade to 700PE in the future. It is anticipated that construction of the scheme will proceed in 2008 subject to completion of formal agreement between Sligo County Council and the developer. The contract costs for the scheme is €624,500. Riverstown SewerageThis project involves the upgrading of the existing wastewater treatment plant in Riverstown to provide automated fine screening and flow measurement. Works are now complete. The estimated cost is €92,000. Ballymote SewerageThis project involves the upgrading of the existing wastewater treatment plant to provide automated fine screening and flow measurement. Works are substantially complete. The estimated project cost is €92,000. Ballinafad Sewerage SchemeThis scheme involves the construction of a new wastewater treatment plant with a design capacity of 350PE in the village of Ballinafad. The scheme is currently with the Tubbercurry/Grange/Strandhill Scheme for procurement purposes. A temporary plant upgrade is currently being put in place pending construction of the new plant. The cost estimate for the scheme is €600,000. Collooney SewerageThis project involves the upgrading of the existing inlet works at the treatment works to provide enhanced screening and inflow measurement. Works are ongoing at present. The estimated project cost is €100,000. Lough Easkey WTPImprovement works were carried out at the water treatment plant including replacement of filter media and lamella plates in the clarifiers. The estimated cost of the works is €180,000.A review of the plant process is ongoing to determine further improvement works required. North Sligo WTPFilter media and the lamella plates were also replaced in the north Sligo water treatment plant. Temporary additional storage capacity for wastewater settlement is currently being installed and Part 8 planning for the installation of a sludge holding tank is due before the Council in April 2008. The preliminary cost estimate for the works is €200,000. Calry PipelineThis scheme involves the installation of approximately 2km of trunk main to service the Calry No.2 PWS scheme from the new water treatment plant at Kilsellagh. The new pipeline is currently being commissioned and will be operational following completion of the Glackbaun GWSS. The cost estimate is €200,000. Ballinascarrow WTPThis scheme involves the refurbishment of the existing water treatment plant at Ballinascarrow as well as the provison of new fencing and railings. The cost estimate is €100,000. 2008 SchemesSome new schemes proposed for 2008 which are subject to DEHLG funding approval are: Easkey Sewer Network Improvements (€250,000); Enniscrone Sewer Network Improvements (€200,000); Tubbercurry Sewer Network Improvements (€300,000); CSO Screens (€150,000). GROUP WATER SCHEMES
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Project | Estimate Cost (€) | % Local | SCC Cost (€) |
|---|---|---|---|
| Sligo Main Drainage (WwTP) | 25,785,664 | 0.282 | 7,271,557 |
| Sligo Main Drainage (Sludge) | 3,039,062 | 0.344 | 1,045,437 |
| Enniscrone WwTP | 4,882,298 | 0.280 | 1,367,043 |
| Teesan/Lisnalurg SS | 3,700,000 | 0.600 | 3,013,239 |
| Kilsellagh WTP | 9,618,982 | 0.235 | 2,260,461 |
| Tubbercurry/G/S WwTP’s | 9,242,320 | 0.600 | 5,545,392 |
| Mullaghmore WSS | 610,018 | 0.248 | 151,284 |
| Sligo SS (Network) | 5,687,695 | 467,795 | |
| Carraroe SS | 2,600,000 | 0.300 | 780,000 |
| Cummeen SS | 2,300,000 | 0.300 | 690,000 |
| Ballincar/Cregg/RP SS | 3,899,869 | 0.192 | 748,775 |
| Lough Talt WSS | 34,658,910 | 0.300 | 10,397,673 |
| Cliffoney | 5,046,811 | 0.600 | 3,028,087 |
| Ballinacarrow | 3,336,723 | 0.600 | 2,002,034 |
| Ballygawley SS | 3,592,121 | 0.300 | 1,077,636 |
| Mullaghmore SS | 9,468,590 | 0.300 | 2,840,577 |
| Ballymote SS | 3,000,000 | 0.300 | 900,000 |
| Collooney SS | 3,000,000 | 0.300 | 900,000 |
| North Sligo WSS | 4,000,000 | 0.300 | 1,200,000 |
| Sligo and Environs WSS | 4,000,000 | 0.300 | 1,200,000 |
| Water Con - Ph. 3( County ) | 39,382,847 | 0.100 | 3,938,285 |
| Total WSIP | 180,851,910 | 50,825,275 |
| Project | Estimate Cost (€) | % Local | SCC Cost (€) |
|---|---|---|---|
| Coolaney WwTW | 1,645,260 | 100% | 1,645,260 |
| Dromore West WwTW | 1,416,000 | 100% | 1,416,000 |
| Carney West WwTW | 1,455,406 | 100% | 1,455,406 |
| Gurteen WwTP | 1,622,993 | 100% | 622,993 |
| Coolaney Water Supply | 252,000 | 100% | 252,000 |
| Ballintogher WwTP | 1,420,345 | 100% | 1,420,345 |
| Castlebaldwin WwTP | 1,393,680 | 100% | 1,393,680 |
| Rockfield WwTP | 175,000 | 100% | 175,000 |
| Bunninadden WwTW | 650,000 | 100% | 650,000 |
| Carraroe (WILT Zoning) | 4,000,000 | 100% | 4,000,000 |
| Total Development Levies | 14,030,684 | 14,030,684 |
| Project | Estimate Cost (€) | % Local | SCC Cost (€) |
|---|---|---|---|
| Improvement of Riverstown WwTW | 92,000 | 25% | 23,000 |
| Improvement of Ballymote WwTW | 92,000 | 25% | 23,000 |
| Cloonacool Network | 150,000 | 25% | 37,500 |
| Improvement of Collooney WwTW | 100,000 | 25% | 25,000 |
| Ballinafad WwTW | 600,000 | 25% | 150,000 |
| Lough Easkey WTP | 180,000 | 25% | 45,000 |
| North Sligo WTP Sludge Facility | 200,000 | 25% | 50,000 |
| Calry Pipeline | 200,000 | 25% | 50,000 |
| Ballinascarrow WTP | 100,000 | 25% | 25,000 |
| Easkey Network Improvement | 250,000 | 25% | 62,500 |
| Enniscrone Network Improvement | 200,000 | 25% | 50,000 |
| Tubbercurry Network Improvement | 300,000 | 25% | 75,000 |
| CSO Screens | 150,000 | 25% | 37,500 |
| Total Small Schemes | 1,864,000 | 428,500 | |
| Overall Total Costs | 196,746,594 | 65,284,459 |